PetroEnergy - Field Surface Facilities Phase
Client : Petro Energy
Value : 13,623,000 USD
Duration : Two Year Service order Contract
Status : Completed
Contractor : Ram Energy
SUMMARY OF THE SCOPE:
PROCUREMENT, CONSTRUCTION & COMMISSIONING FOR FNE FILED:
One (1) Oil Gathering Manifold (OGM) consist of 4 Oil Wellheads
along with 7 km of 4 Flow Line, 4 km of 10 Trunk Lines,
12.860 Km of 12 Crude Oil Transit line & 12.860 Km of 6 Gas
Transit line
Projects
- EPCC services Hydro Protection & Drainage Str
- Shendi-el Matama Bridge
- Algaili Water Treatment Plant
- Tharjath Bio-Remediation
- Manga Bio-Remediation
- Unity Bio-Remediation
- Field Improvement Project Phase - I
- Field Improvement Project Phase - II
- Hadeeda Pipeline Joint Repair From KM-02 TO K
- PetroEnergy - Field Surface Facilities Phase
- Field Surface Facilities Phase (Phase II)
- Field Surface Facilities Phase 5 (FSF-5)
- Field Surface Facilities Phase 4 (FSF-4)
- EPCC of South Annjma Facilities Package Proje
- Greater Neem Export Pipeline
- LGP Tanks
- Field Improvement Project Phase III
- EPCC of Compact Substation
- EPCC of Tomasouth New Switchgear
- EPCC of Baleela Warehouse
- Over Head Transmission Line Project
- EPCC of Baleela New Air Port